Mary Lanyon Fay Elementary School, San Diego, CA

  • warning: Parameter 1 to theme_field() expected to be a reference, value given in /var/www/yin80.com/htdocs/includes/theme.inc on line 171.
  • : Function ereg() is deprecated in /var/www/yin80.com/htdocs/includes/file.inc on line 646.
  • : Function ereg() is deprecated in /var/www/yin80.com/htdocs/includes/file.inc on line 646.
  • : Function ereg() is deprecated in /var/www/yin80.com/htdocs/includes/file.inc on line 646.
  • : Function ereg() is deprecated in /var/www/yin80.com/htdocs/includes/file.inc on line 646.
  • : Function ereg() is deprecated in /var/www/yin80.com/htdocs/includes/file.inc on line 646.
  • : Function ereg() is deprecated in /var/www/yin80.com/htdocs/includes/file.inc on line 646.
  • : Function ereg() is deprecated in /var/www/yin80.com/htdocs/includes/file.inc on line 646.
  • : Function ereg() is deprecated in /var/www/yin80.com/htdocs/includes/file.inc on line 646.
  • warning: Parameter 1 to theme_field() expected to be a reference, value given in /var/www/yin80.com/htdocs/includes/theme.inc on line 171.

The new construction project was conducted under Proposition MM. The 6.3-acre site houses a new elementary school, which includes 32-classrooms, 61,000 square-feet of facilities, and parking to accommodate 58 vehicles. Other features consist of a joint-use field for soccer and baseball, a multipurpose room, library/media center, lunch shelter, elevator and accessibility features, kitchen, faculty lounge, workroom, and administrative center. SCS&T provided the following services:
 
Geotechnical Services: Observation & Testing of Grading, Underground Utilities, Backfill, Subgrade, Base Material, and Asphalt
 
Special Inspection & Materials Testing: Concrete, Masonry, Welding, Post-Tension Concrete
 
Third Party QA/QC Services: Waterproofing